The start of the school year could be a bit chaotic for some students thanks to ongoing construction in the capital city.
Work on Elizabeth Avenue, University Avenue, Prince Philip Drive and the Allandale Road Bridge continues, affecting routes to and from the university, St. Andrews Elementary and Prince of Wales Collegiate.
Elizabeth Avenue from Bonaventure to Westerland Road is now open, while the portion from Westerland Road to Freshwater Road remains closed with work expected to completed by November.
Westerland Road meanwhile is now open.
Work continues on University Avenue and Prince Philip Drive with construction scheduled to be completed in October.
Traffic delays will continue at the Allandale Road Bridge. That work is expected to be done by October.