We’ll be getting an update on Muskrat Falls today.
Nalcor president and CEO Stan Marshall will go before the media over the lunch hour to talk about the project, which has faced its fair share of troubles.
The power dams are built, but Newfoundland and Labrador Hydro continues to run into problems with equipment at Soldiers Pond and the GE software to deliver the power.
The latest cost of the project is $12.7-billion, a figure which many critics expect to rise.
VOCM News will be there.